Wednesday, November 24, 2021

Holes 1 and 2 Progress

 


Hole #1 is nearing completion with all shaping finished, sod installed, and stone in place. The Better Billy Bunker liner is scheduled to be sprayed today and bunker sand should be installed early next week.


Pictured above is work being completed on #2 fairway bunkers. These 3 bunkers were rebuilt into 1 larger bunker. As seen, sod was stripped across the fairway so that a new bunker drainage outlet could be installed.



In this picture you can see that hole #2 is nearing completion. All stone should be completed by the end of the day. Sod will be finished next week.